Planned maintenance on the Incapsula data center in Chicago
Scheduled Maintenance Report for Imperva
Completed
Maintenance on the Chicago data center has been cancelled.
Posted Oct 24, 2018 - 03:02 UTC
Update
We will be undergoing scheduled maintenance during this time.
Posted Sep 25, 2018 - 05:54 UTC
Update
Maintenance on the Chicago data center has been rescheduled to Wednesday, October 24th, 2018 at 05:00 UTC. We expect to complete the maintenance by Wednesday, October 24th, 2018 at 13:00 UTC.
Posted Sep 25, 2018 - 05:50 UTC
Update
Maintenance on the Chicago data center has been rescheduled to Wednesday, September 26th, 2018 at 05:00 UTC. We expect to complete the maintenance by Wednesday, September 26th, 2018 at 13:00 UTC.
Posted Aug 27, 2018 - 18:36 UTC
Update
Maintenance on the Chicago data center has been rescheduled to Monday, September 24th, 2018 at 07:00 UTC. We expect to complete the maintenance by Monday, September 24th, 2018 at 12:00 UTC.
Posted Aug 26, 2018 - 22:59 UTC
Update
Maintenance on the Chicago data center will be performed on Monday, August 27th, 2018 at 07:00 UTC. We expect to complete the maintenance by Monday, August 27th, 2018 at 11:00 UTC.
Posted Aug 23, 2018 - 08:39 UTC
Update
Maintenance on the Chicago data center will be performed on Monday, August 27th, 2018 at 13:00 UTC. We expect to complete the maintenance by Monday, August 27th, 2018 at 17:00 UTC.
Posted Jul 25, 2018 - 16:50 UTC
Scheduled
Maintenance on the Chicago data center will be performed on Thursday, July 26th, 2018 at 11:00 UTC. We expect to complete the maintenance by Thursday, July 26th, 2018 at 22:00 UTC.
Posted Jun 21, 2018 - 15:22 UTC
This scheduled maintenance affected: North American PoPs (Chicago 1, IL (ORD)).