Planned maintenance on the Incapsula data center in Sao Paulo
Scheduled Maintenance Report for Imperva
Completed
Maintenance on the Sao Paulo data center has been completed.
Posted Dec 05, 2018 - 13:52 UTC
Update
Maintenance on the Sao Paolo data center has been extended to Wednesday, December 5th, 2018 at 14:00 UTC.
Posted Dec 05, 2018 - 11:30 UTC
Update
Maintenance on the Sao Paolo data center has started. Network traffic has been diverted to an alternate regional data center.
Posted Dec 05, 2018 - 07:00 UTC
Scheduled
Maintenance on the Sao Paulo data center will be perfomed on Wednesday, December 05th, 2018 at 07:00 UTC. We expect to complete the maintenance by Wednesday, December 05th, 2018 at 12:00 UTC.
Posted Nov 06, 2018 - 23:18 UTC
This scheduled maintenance affected: LATAM PoPs (Sao Paulo 1, Brazil (GRU)).