Essential maintenance on the Incapsula data center in Newark
Scheduled Maintenance Report for Imperva
Completed
Maintenance on the Newark data center has been completed.
Posted Dec 02, 2018 - 15:54 UTC
In progress
Maintenance on the Newark data center has started. Network traffic has been diverted to an alternate regional data center.
Posted Dec 02, 2018 - 07:59 UTC
Update
Maintenance on the Newark data center will be performed on Sunday, December 2nd, 2018 at 08:00 UTC. We expect to complete the maintenance by Sunday, December 2nd, 2018 at 16:00 UTC.
During this time, traffic will be rerouted to the closest data center, with no expected interruption of service.
Infrastructure Protection customers should route traffic to the secondary data center.
Posted Nov 28, 2018 - 14:58 UTC
Scheduled
Maintenance on the Newark data center will be performed on Sunday, December 2nd, 2018 at 08:00 UTC. We expect to complete the maintenance by Sunday, December 2nd, 2018 at 12:00 UTC.
During this time, traffic will be rerouted to the closest data center, with no expected interruption of service.
Infrastructure Protection customers should route traffic to the secondary data center.
Posted Nov 25, 2018 - 11:36 UTC
This scheduled maintenance affected: North American PoPs (New York 1, NY (NYC)).